When is the best time to start talking about automation

Cheapest and safest before the electrical design. Below we set out what actually changes at every later stage of construction, and what catching up costs.

Apartment floor plan with a smart home installation design

Stage 1: before the electrical design

The electrical design is drawn up with automation assumed from the start: sensor cabling, buses, spare room in the switchboard and control points where they will actually be needed. The cost then comes down to devices and labour — with no rework.

A cable run at shell stage costs a few złoty. The same cable after the walls are finished means chipping off plaster, repainting and a week of delay.

Stage 2: installation work under way

Still a good moment, as long as the electrical crew has not closed up the chases. Usually we manage to add the bus and the sensors; sometimes some of the metering points have to be dropped.

Stage 3: a finished house

This is where wireless and point solutions come in: lighting control inside existing boxes, thermostats, blinds, the alarm. Full integration is possible, but the scope is narrower and the cost per function higher.

What to do right now

  • Write down the functions that must be working on the day you move in.
  • Ask your electrician for spare room in the switchboard — at least 30%.
  • Decide on shading before you order the windows and blinds.
  • Establish who will program the logic — that is a separate skill from installation.

What stage are you at? We will review the design and tell you what can still be done.